Ugandan families displaced and left to struggle by Chinas’s mega dam

Published

on

Construction of the Karuma dam has deprived hundreds of people in Uganda’s Nile delta of their land, homes, and livelihoods. Many people have been waiting a decade for relocation, with some left to live under high voltage transmission lines for lack of safer alternatives. 

From a height above the riverbank, you can watch the massive concrete dam harness the powerful waters of the Victoria Nile River. When the hydropower plant is completed by Chinese company Sinohydro Corporation Limited, it is expected to produce 600 megawatts for the Ugandan electricity market.

The Karuma dam project has been delayed several times, forcing the government to start paying off the loan to the Export-Import Bank of China.

The hillside upstream of the river is one of the few places where you can see the whole power station. The transmission substation and part of the riverbank are fenced off and guarded by the military. Two tall surveillance towers have been built to keep intruders outside the area.

After the construction work started ten years ago, the people in Awoo village lost most of the land they had cultivated for generations, and access to the river where they fished. Out of desperation, some of the villagers started to produce gravel from a large mound of rocks excavated from the river basin and dumped next to their homes during the dam’s construction. Men and women make the hazardous 30-meter climb up the deposit to collect the stones, which are then cracked manually with hammers and sold to construction companies.

Out of desperation, some villagers started to produce gravel from a large mound of rocks excavated from the river basin.

A report by Both ENDS describes how land evictions from Awoo village were forceful, with bulldozers bringing down houses, fruit trees and other properties as the community watched. A family was reportedly forced out of their house, which was then set on fire. After that, the community had no choice but to accept the limited compensation offered to them and determined by the Ugandan state.

Today, those who do not make a living from cracking stones have few options other than doing hard labour for the power company. Normally they earn UGX 8000 a day (about US$2) for cleaning or heavy concrete work, according to the interviews by Just Finance International. This salary is only enough to buy food, they claim.

When the project first started a decade ago, they were promised relocation to somewhere better and fair compensation for their land. This has not happened. We observed several families living under the high voltage transmission line that connects the power station to the grid which is both hazardous for the health and risky. Still, people claim they have nowhere else to go, a failure that has been flagged as a weakness by Uganda’s auditor general.

Chinese state-owned company Sinohydro started construction of Karuma in 2013, as well as three high-voltage transmission lines. The infrastructure is a keystone project in the government’s plan to electrify Uganda, where only 22.1 percent of the population have access to the grid. The Karuma hydro plant is expected to power homes, industry, and public buildings such as schools and hospitals.

The project has been delayed several times, forcing the government to start paying off the $1.7-billion loan to the Export-Import Bank of China before any electricity was produced. The hydro plant is now generating power but not at its full capacity.

The communities around the dam had high expectations when construction started. The government promised well paid work, roads, a school, a health center, access to water, electricity and a fishpond.

However, community members interviewed by Just Finance, claim that little has been completed. Not even the promise of healthcare access was fulfilled. The closest hospital is in Gulu, 65 km from the village. Another health center was constructed by Sinohydro in the town Masindi, 112 kilometers away from the villages. This investment is claimed to benefit the communities affected by the dam, but according to Just Finance sources, it serves the military and not the general public.

Furthermore, the promised water supply is still missing and the garbage collection center for Karuma township has also not been completed.

A church has been built. A primary school has been renovated. And a mosque is being renovated although the building has been rejected by the Muslim community because of its poor build quality. The communities still have no access to the roads and, ironically, no one in the communities visited by Just Finance, had access to electricity.

In Ayuda village, not far from Awoo, the situation is desperate. Despite all the promises from the government and the Chinese company, living conditions have deteriorated. Many families in the village can no longer afford school fees, and they have to walk a long distance to fetch water from springs in the jungle.

Men and women make the hazardous 30-meter climb up the deposit to collect the stones, which are then cracked manually with hammers.

“Our life has been overturned”, a woman told Just Finance.

According to the villagers, more than 100 acres of land have been taken from them, with just one acre remaining. The community say they were offered 6 million UGX (1600 USD) for the land, an amount they all thought was far too low, but nobody listened, and they had to take the case to court. The process is ongoing after 10 years.

One woman told Just Finance that she used to sell her harvest on the market and earn good money, but now she has nothing to sell. To survive, they have to work for the Chinese company. It is hard labour, and her salary of UGX 8000 per day is only enough to buy food, she said.

The Ayuda village had more than 150 graves in the project area. Construction works have destroyed many of them, according to people in the community. No one got any compensation to move the graves.

“It is an evil omen when the graves are destroyed. It will affect our community mentally for generations to come,” one woman said.

The community members find it difficult to communicate with people from the Chinese company. There are no translators, and the government does not help them. This has caused misunderstanding and mistrust.

One woman claimed she had 8 acres of land before the hydro plant was built, of which 5 were farmland. But when her land was evaluated by the government, they wrote that she only had 3 acres.

“It was a fraud, and somebody else got the money. I have no money left and I have no land anymore. Instead of creating development this has worsened our situation and destroyed our community,” the woman said.

Just Finance International has contacted Sinohydro Corporation Limited and Ugandan electricity company, Uganda Electricity Generation Company Limited (UEGCL), but to date they have not yet provided a response.

Source: justfinanceinternational.org

Continue Reading

NGO WORK

World Bank Fails to Remedy Harms it Caused in Tanzania, Despite a Scathing Investigation by its Inspection Panel

Published

on

Oakland, CA – A scathing investigation by the Inspection Panel of the World Bank confirms the responsibility of the Bank in enabling the expansion of Ruaha National Park and related severe human rights abuses in Tanzania. The Panel confirms “critical failures” of the institution in the planning and supervision of the Resilient Natural Resource Management for Tourism and Growth (REGROW) project that resulted in “serious harm” to communities and violated Bank’s safeguards and operating procedures.1

“The independent Inspection Panel has confirmed the Bank’s grave wrongdoing which devastated the lives of communities. Pastoralists and farmers who refused to be silenced amidst widespread government repression, are now vindicated, and Bank’s efforts to sweep human rights abuses under the rug laid bare,” said Anuradha Mittal, Executive Director of the Oakland Institute.

The REGROW project enabled the government to expand the Ruaha National Park and move ahead with eviction plans – formalized in October 2023 through Government Notice 754. The Bank directly funded TANAPA rangers who committed atrocities with no oversight. In a drastic turn from its initial defense of the project, the financial institution has been forced to recognize “weaknesses in the project design, preparation, implementation, and Bank supervision.” As a result, at least 84,000 people from 28 villages face eviction while pastoralists and farmers have suffered gruesome human rights abuses by Bank-funded rangers and over US$70 million in economic damages.

In documents made available today, the Bank’s management concedes that by “enhancing TANAPA’s capacity to enforce the law,” the project “increased the possibility of violent confrontations” between rangers and villagers. The Inspection Panel found the Bank to have failed to adequately supervise TANAPA and to be unaware of the agency’s operating framework which permits the rangers to use “excessive force,” in violation of international standards. As documented by the Institute, over the course of the project, at least 11 individuals were killed by police or rangers, five forcibly disappeared, and dozens suffered physical and psychological harm, including beatings and sexual violence. The Bank provided TANAPA rangers with 21 different types of equipment to strengthen their patrolling capacity in the project area – including bush knives that the Panel found “could potentially have been used to burn or strip naked” Maasai women in a May 2023 incident.

The Panel’s report documents the timeline of Bank’s failure to act after April 2023, when it was informed by the Oakland Institute about the abuses and violations of its safeguards. Instead, the Bank disbursed over US$33 million to the project over the next year. REGROW task team leader, Enos Esikuri, even publicly stated that the Bank was “very impressed with what is going on,” when meeting with government agencies implementing the project. In April 2024, disbursements were finally suspended as a result of Tanzania’s noncompliance with Bank safeguards, followed by cancelation of the project in November 2024.

“The World Bank failed to act after it was informed of the harms it was financing. It continued disbursements for a full year, allowing cattle seizures and farm closures to drain family savings, kept children out of school, and let TANAPA rangers murder more innocent villagers with impunity. No institution is above law and can be allowed to get away with crimes like this,” said Mittal.

The Bank’s Executive Directors, however, approved the Management Action Plan (MAP) that does not address the Panel’s findings. In blatant disregard of the facts and official documentation, the World Bank has conveniently refused to acknowledge its responsibility in allowing the park expansion, which it falsely claims took place prior to the project.  It is this expansion of Ruaha National Park that triggered murders, evictions, and decimated livelihoods. The MAP delusionally places trust in the government that there will be no resettlement while it is already well underway. The impacted communities conveyed their rejection of the MAP to the Bank’s Board and called for it to remedy the harms caused by park’s expansion by reverting boundaries to the 1998 borders, suspending livelihood restrictions, resuming basic services, and providing justice and reparations for victims.

“Instead of remedying harms identified by the Panel, the MAP patches together two projects that have nothing to do with REGROW and are in no way designed to provide redress. The Action Plan put forward by the World Bank is beyond shameful. Suggesting that tens of thousands of people forced out of their land can survive with “alternative livelihoods” such as clean cooking and microfinance is a slap on the face of the victims. It demonstrates World Bank’s continued lack of remorse for harms financed by tax dollars and makes a mockery of its own accountability mechanism. Financing of this institution – responsible for misery of the poor instead of ending poverty – must be challenged,” commented Mittal.

Despite fear of retribution from Tanzania’s repressive regime, the impacted communities were relentless in demanding justice till they forced the cancellation of the project. “For years we have waited for the World Bank to fix the disaster it created. Today the Board of the Bank has undoubtedly failed in its own mission, but we will not give up, no matter what it takes,” said a community representative.

“The World Bank’s financing commitments for operations in Tanzania amount to US$10 billion. It does have the leverage and authority to fix this catastrophe. The United States, as the largest shareholder and funder of the World Bank Group, must also take responsibility,” concluded Mittal.

Source: oaklandinstitute.org

Continue Reading

NGO WORK

The World Bank Must Be Held Accountable for Harm Inflicted on Tanzanian Communities by Tourism Project

Published

on

The World Bank’s Board of Executive Directors is reviewing the Action Plan (MAP) prepared by the Bank’s management to address the findings of the Inspection Panel’s investigation into the Resilient Natural Resource Management for Tourism and Growth (REGROW) project in Tanzania. The investigation followed a complaint filed by the Oakland Institute in June 2023 on behalf of impacted communities. While the Panel’s findings and MAP will only be made public after its approval by the Board, the Oakland Institute urges the Bank to ensure that demands of impacted communities are addressed by the MAP to redress the harms caused.

“The Bank is responsible for the devastating crisis which has left over 84,000 lives hanging in the balance. For several years, using tax-payer dollars, it financed a project that blatantly violated its operating procedures and safeguards around human rights abuses and forced resettlement. It failed to act when made aware of the violations and continued pouring money into the project. Now the Bank cannot hide behind lame excuses and should fulfil the demands of communities harmed by its financing,” said Anuradha Mittal, Executive Director of the Oakland Institute.

Beacon marking expansion of Ruaha National Park to consume Luhanga village and make communities trespassers in their own lands
Beacon marking expansion of Ruaha National Park to consume Luhanga village and make communities trespassers in their own lands

The US$150 million REGROW project in Tanzania began in 2017 as a credit from the International Development Association (IDA). It was cancelled on November 6, 2024 after nearly two years of advocacy by the Oakland Institute and affected villagers to hold the Bank accountable for enabling the expansion of Ruaha National Park (RUNAPA) and supporting TANAPA, the paramilitary Tanzania National Parks Authority. Its rangers, equipped and financed by the Bank, are responsible for egregious human rights abuses, including extrajudicial killings, forced disappearances, and crippling livelihood restrictions that have terrorized local communities. Forced resettlement was initiated by the Tanzanian government in complete disregard for the Bank’s safeguards that require proper consultation and adequate compensation for affected communities.

“We call on the World Bank to fully assume its responsibility and urgently take these necessary steps to answer our pleas for justice. Our lives are on hold as the threat of eviction looms over us every single day. Our livelihoods have been undermined for years, our children are out of school, our farms sit fallow and our cattle are still being forcibly seized. We cannot continue living like this. The Bank must adequately address our past and ongoing suffering.”

Statement by impacted villagers in Mbarali, January 2025

In December 2024, the Institute worked with the impacted communities to carry out a thorough assessment on the ground to evaluate the consequences of the REGROW project. This research lays bare the devastation caused by the expansion of the park – formalized during the project in October 2023 through Government Notice 754. While the Tanzanian government claims only five villages are now inside RUNAPA, the December assessment found that 28 villages across 10 wards and home to over 84,822 people are located inside the area added to the park. As Tanzanian law forbids settlement in National Parks, these farmers and pastoralists will be forcibly evicted unless the expansion is revoked.

Livelihood restrictions enforced by TANAPA rangers have decimated these communities. Thousands of farmers have been barred from farming by the government. For 551 members of two farmer associations stopped from cultivating rice over the past three years, the economic loss is over US$66 million.1

Herders have also been massively impacted by the restrictions of access to pasture land, cattle seizures, and violence committed by TANAPA rangers. Since 2021, 52 pastoralist families have had cattle seized, losing 7,579 cattle for a value of over US$6 million.2 Since 2018, 39 families have paid the equivalent of US$212,175 in fines to recover 4,757 cattle confiscated by TANAPA within disputed park boundaries. These fees and fines have pushed families into destitution.

Over the course of the project, at least 11 individuals were killed by police or rangers, five forcibly disappeared, and dozens suffered physical and psychological harm, including beatings and sexual violence. Victims and their relatives have lost hope of seeing TANAPA rangers brought to justice while continued repression has stopped many from speaking out.

“The World Bank claimed the project was intended to benefit local communities; it has instead destroyed their lives. It must take responsibility for enabling violence and displacement and ensure that the expansion of the park is revoked,” concluded Mittal.

Impacted communities are demanding that the MAP address the following urgent issues:

  1. Removal of beacons placed marking the expansion of the park and to officially revert park boundaries to the 1998 borders established by GN 436a.
  2. Provide comprehensive compensation for damages incurred by livelihood restrictions and violence inflicted by TANAPA rangers, including:
    1. Value of fines paid by pastoralists to reclaim cattle illegally seized.
    2. Value of cattle auctioned.
    3. Compensation for the loss of agricultural production for three seasons (2023, 2024, 2025).
    4. Compensation for the victims of violence and killings by TANAPA.
  3. Establish a multistakeholder independent mechanism to oversee reparations.
  4. Restore social services to villages impacted by GN 754.
    1. Complete construction on Luhanga Secondary School and provide it with government teachers.
    2. Reopen Mlonga Primary School that was closed in October 2022.
    3. Ensure all villages located within GN 754 boundaries are provided with the power, water, and social services they are entitled to like other villages.

S0urce: oaklandinstitute.org

Continue Reading

NGO WORK

Business, UN, Govt & Civil Society urge EU to protect sustainability due diligence framework

Published

on

As the publishing date for the European Commission’s Omnibus Simplification Package proposal draws closer, a coalition of major business associations representing over 6000 members, including Amfori and the Fair Labor Association, has called on the EU to uphold the integrity of the EU sustainability due diligence framework.

Governments have also joined the conversation, with the Spanish government voicing its strong support for maintaining the core principles of the CSRD and CSDDD.

Their call emphasises the importance of preserving the integrity of the Corporate Sustainability Due Diligence Directive (CSDDD) and Corporate Sustainability Reporting Directive (CSRD).

These powerful business voices have been complemented by statements from the UN Working Group on Business & Human Rights, alongside 75 organisations from the Global South and 25 legal academics, all cautioning the EU against reopening the legal text of the CSDDD.

Additionally, the Global Reporting Initiative has urged the EU to maintain the double materiality principle of the Corporate Sustainability Reporting Directive, meanwhile advisory firm Human Level published a briefing exploring the business risks of reopening level 1 of the text.

Concerns stem from fears that reopening negotiations could weaken key human rights and environmental due diligence provisions, undermine corporate accountability and create legal uncertainty for businesses.

The European Commission’s Omnibus proposal is expected to be published on 26 February.

Source: Business & Human Rights Resource Centre

Continue Reading

Resource Center

Legal Framework

READ BY CATEGORY

Facebook

Newsletter

Subscribe to Witness Radio's newsletter



Trending

Subscribe to Witness Radio's newsletter