The East African Court of Justice has set Wednesday the 29th of November, 2023 to deliver a ruling on a petition challenging the construction of the East Africa Crude Oil Pipeline (EACOP) Project filed by four East African Non-governmental Organizations.

The Court consists of Honorable Mr. Justice Yohane Bokobora Masara Principal Judge, Honorable Justice Dr. Charles Nyawello Deputy Principal Judge, Honorable Mr. Justice Richard Muhumuza, Honorable Mr. Justice Richard Wejuli, and Honorable Justice Dr. Gacuko Leonard.

According to the ruling notice seen by Witness Radio, the regional Court will deliver the ruling at 9:30 East Africa Standard Time, the 29th of November 2023.

On 6 November 2020, Natural Justice, Africa Institute for Energy Governance (AFIEGO), Centre for Strategic Litigation and the Centre for Food and Adequate Living Rights (CEFROHT) Limited filed a petition against the governments of Uganda and Tanzania and the Secretary General of the East African Community (EAC) challenging the construction of the EACOP project. 

The basis of the Applicants’ petition rests on the assertion that the EACOP project violates multiple provisions of the Treaty of the Establishment of East African Community. The project further violates the Protocol for the Sustainable Management of the Lake Victoria Basin, the African Charter on Human and People’s Rights, the African Convention on Conservation of Natural Resources, the post–2020 Convention on Biological Diversity, and the Paris Climate Accords.

Furthermore, the Applicants argue that the entities backing the EACOP project, such as Total Energies, China’s National Offshore Oil Corporation, and the Governments of Uganda and Tanzania, failed to carry out thorough and meaningful public engagement and consultation processes and additionally did not conduct comprehensive assessments of both the human rights and climate impacts before initiating the EACOP project.

In 2006, Uganda discovered commercially viable oil reserves in the Albertine Graben region, specifically in the Lake Albert area near Hoima district.

With the cooperation and support of its neighbor, Tanzania, the two governments approved in March 2023 the construction of the $5 billion EACOP project, which is planned to cover a distance of 1,443 kilometers.

The East Africa Crude Oil Pipeline (EACOP) connects the Tilenga and Kingfisher oilfields in western Uganda with the port of Tanga in eastern Tanzania, when completed, the project will be the longest heated crude oil pipeline in the world crossing through 10 districts in Uganda, and 25 districts in Tanzania.

Uganda’s President, Mr. Yoweri Museveni Tibuhaburwa, has often celebrated the oil projects calling a success. He firmly believes that the oil discovery represents a significant catalyst for economic development and will bring benefits to the local communities, but the current reality is a reverse to his statements.

The EACOP project has triggered significant concerns among communities and civil society groups due to its detrimental impacts on thousands of individuals in Uganda and Tanzania. The most affected have been the Project Affected Persons (PAPs) and human rights activists who stand against the project. Reports have highlighted cases of land grabbing, the displacement of host communities, inadequate compensation, and the troubling trend of harassing and arresting community leaders and rights activists.

It should be remembered that on the 14th of September 2022, the European Union Parliament passed an advisory resolution to suspend the oil pipeline for a year citing disastrous human and environmental rights violations associated with the project.

The resolutions put forth by the European Parliament legislators echo the distressing issues raised by affected communities regarding the oil pipeline project.

In response to the violation of human rights, conventions, and treaties, Civil Societies including Natural Justice, AFIEGO, Centre for Strategic Litigation, and CEFROHT took the pivotal step of approaching the East African Court of Justice to challenge the construction of the EACOP project.